Garage and shed roofs
A single garage is commonly one to two days for removal. Double garages and blocks take longer. A new roof adds time.
Ceilings and Artex
Usually a day per room or two, depending on enclosure set-up, drying time and clean-down.
Licensed jobs
Notification takes at least 14 days before work starts. The work itself can take days to weeks.
Farm and commercial roofs
Large areas are phased. Weather, platform hire and waste runs decide the programme.
What slows a job
Bad weather on roofs, poor access, extra material found, and clearance testing.